EC Stalowa Wola - Able to finish power unit

The agreement for completion in the EPCM formula of the 449 MW power unit in the Stalowa Wola CHP Plant, in consortium consisting of EPK and Power Research & Testing Company „ENERGOPOMIAR” Ltd, was signed on Tuesday, 17th October 2017.

The subject of the order is execution of design and engineering work as well as management and supervision over implementation of construction and assembly work. The contract also includes supervision over the implementation of the commissioning process and assisting the Purchaser in the organization of tender procedures for the selection of contractors for particular work areas.

PGNiG, Tauron and Stalowa Wola CHP Plant in October last year signed a conditional agreement and annexes regarding "Construction of a CCGT in Stalowa Wola", which gave the opportunity to resume work in the project and to complete the investment in the Stalowa Wola CHP Plant. The investment, advanced in 85 percent, was waiting for the resumption of work from January 2016.
The final offers were not submitted by the two other entities, that were invited to the competitive dialogue, the consortium of GE Power (Poland), General Electric International and the consortium: Tractebel Engineering (Poland), Tractebel Engineering (Belgium). In September 2017, our offer was chosen as the most advantageous one. The deadline for the contract will be 26 months from the entry into force of the contract and will end no later than 31st December 2019.

Get in Touch

ENERGOPROJEKT-KATOWICE SA

Poland, 40-159 Katowice
15th Jesionowa Str.

+48 32 2089 215

epk@epk.com.pl